To reduce NPT in drilling with AI, use it for the part people never have time for. It reads every time-log line in the daily drilling reports, classifies each hour of lost time the same way across every well, ranks the causes that keep coming back, and puts hours and cost against each one. People then fix the top three causes and measure whether they stay fixed. AI does not cut NPT on its own. It makes the evidence complete and consistent enough that the right fixes get chosen.

Why most NPT numbers cannot be trusted

Every drilling team reports non-productive time. Few can say with confidence which three causes cost them the most hours across the last ten wells. The reasons are always the same.

  • NPT lives in free text. The driller types "WOW, crane down, waited on boat", and the code chosen depends on who is on tour.
  • Codes differ between operator, contractor and service company. IADC's DDR Plus gives a common structure of activity, sub-activity and equipment codes, and lets companies map their own code sets onto it. In practice, many reports still mix the two.
  • Short delays are never coded. A slow connection or a 20-minute wait for a third-party hand stays inside "drilling" or "tripping".
  • Responsibility is argued, not recorded. Rig problem or well problem decides who pays, so the label is negotiated after the event.
  • Nobody reads across wells. Each DDR is read the morning it arrives, then filed. Repeat causes only show when twenty wells are read together.

Drilling Contractor reported in 2021 that some customers of one large drilling contractor were seeing 20 to 40% overall NPT per well. Whatever your own figure is, you cannot reduce it until it is measured the same way on every well.

NPT and invisible lost time are different problems

An NPT reduction programme needs both, but they come from different data and get different fixes.

Non-productive time (NPT)Invisible lost time (ILT)
What it isTime lost to an event: failure, wait, downhole problemRoutine work done slower than the rig has shown it can do
ExampleTop drive repair, 9 hours; waiting on cement unit, 6 hoursConnections averaging 6 minutes against a demonstrated 4.8
Where it showsDDR time log, usually codedRig-state data from the sensors; rarely in the DDR
How AI finds itReads and classifies DDR textSplits sensor data into rig states and times each one
Typical fixMaintenance, spares, logistics, program changesCrew practice, procedures, rig equipment set-up

A useful method for ILT, published by a drilling analytics vendor, benchmarks each routine operation at a percentile the rig achieves regularly, such as P25, rather than its single best. Each event's lost time is its actual duration minus that benchmark. Total opportunity is the time lost per event multiplied by how often it happens. Their example shows why frequency matters: 30 seconds lost on 250 events is 125 minutes, more than 5 minutes lost on 10 events, which is 50.

How AI classifies NPT from daily drilling reports

This is the step that turns a pile of PDFs into something you can rank. It works in four passes.

1. Extract the time log

Pull every time-log row from every DDR: date, from, to, duration, depth, IADC code if given, and the remark text. Check that each day adds up to 24 hours. Gaps and overlaps are the first data-quality finding.

2. Classify each row

A language model reads the remark and assigns category, equipment, cause and responsible party. The published industry example is a good starting point. Drilling Contractor reported that KCA Deutag manually tagged 40,000 rows of driller comments and trained a model that sorts each new entry into one of five classes: rig problem, well problem, normal operation, HSE event or waiting time. The company reported more than 90% accuracy, with the model running on over 91% of its operated fleet. An earlier arXiv paper took a different cut and labelled report sentences as EVENT, SYMPTOM or ACTION, so the cause and the response could be linked.

3. Check against the code the crew chose

Where the AI's class and the crew's code disagree, list the row for review. These disagreements are where NPT hides: a "circulate" that was really waiting on losses material, or a "trip" that was a trip for a failed motor.

4. Have an engineer confirm

For the first wells, an engineer reviews a sample of classified rows each week. Corrections become examples for the model. This is also how you agree the taxonomy with the contractor before the numbers are used in a commercial discussion.

CategorySub-causes to separateUsual ownerEvidence in the DDR
Rig equipmentTop drive, drawworks, mud pumps, power, pipe handling, BOPContractorRepair rows, equipment named, parts awaited
Downhole toolsMotor, MWD/LWD, bit failure, string washoutService companyUnplanned trips, pressure drops, tool named
WellboreLosses, stuck pipe, tight hole, instability, kick and well controlOperatorLCM pumped, overpull, reaming, mud weight changes
WaitingWeather, transport, third-party crew, materials, ordersVaries; record who"WO" remarks, standby, crew or boat named
Planning and programProgram change, casing point revision, approvalsOperatorWaiting on orders, changed plan
HSEIncident, stop-work, investigationSharedStop-work, incident reference
ILT (from sensors)Connections, tripping speed, back to bottomContractor and operatorNot in the DDR; from rig-state data

Our guide to AI for daily drilling reports covers getting clean DDR data in the first place.

Find repeat causes, not just big events

Once every hour is classified, the ranking is simple arithmetic. Do it three ways, because each points to a different fix.

  • By total hours: the classic Pareto. Usually a short list explains most of the lost time.
  • By count: frequent short events point to procedures and equipment set-up, and are often cheaper to fix.
  • By cost: hours multiplied by the spread rate for that well (rig, services and support per hour).

Then look for patterns a single report cannot show. Does the same formation cause losses on every well? Does one mud pump model fail after the same number of hours? Do waits on the cement unit cluster on one route or one supplier? A language model can answer these questions in plain words, with each claim cited to the report and line.

A worked example (illustrative)

The figures below are illustrative, not from any campaign. Six wells, 210 rig days, NPT classified from the DDRs and priced at an illustrative spread rate of USD 2,500 per hour.

CauseEventsHoursShare of NPTIllustrative cost (USD)
Losses in one carbonate interval911829%295,000
Top drive failures77418%185,000
Waiting on third-party services216616%165,000
MWD failures and unplanned trips45814%145,000
Tight hole and reaming124912%122,500
Other154511%112,500
Total68410100%1,025,000

The table says more than "NPT was 8% of rig time". Losses in one interval are a program problem: the mud and LCM plan for that section. Top drive failures are a maintenance problem with a clear owner. Twenty-one waits on third parties are a logistics problem, small each time and large together. Each needs a different person to act.

Turn the ranking into actions

An NPT study that ends in a slide deck changes nothing. Give each of the top causes an owner, an action and a number to watch.

Repeat causeTypical actionOwnerMeasure
Losses in a known intervalPre-treat with LCM, revise mud weight window, add to next well programDrilling engineerLoss hours in that interval, per well
Rig equipment failuresChange PM interval, stock critical spares on site, check run hours against failuresRig managerEquipment NPT hours per 1,000 operating hours
Waiting on third partiesCall-out lead times in the plan, earlier mobilisation, supplier reviewLogistics or wellsite leadWait hours per well, by supplier
Downhole tool failuresReview with service company, operating limits, back-up tool on siteService company leadFailures per run, mean hours to failure
Slow connections and tripping (ILT)Agree a target per rig, review weekly with crewsToolpusherMedian connection time, trip speed

For wellbore problems, real-time alerts help stop the event while it is building. See stuck pipe early warning with AI. For repeat equipment failures, the work order history usually matters more than another model.

How to start: a pilot on one campaign

  1. Choose a campaign of at least five completed wells in one field, with the DDRs as PDF or exported data, and the spread rate per well.
  2. Agree the NPT taxonomy with the drilling superintendent and the contractor before any number is shown. Use the categories above as a draft.
  3. Classify every time-log row with AI. Have an engineer review a random sample of rows and every row where the AI and the crew code disagree.
  4. Produce three rankings: by hours, by count and by cost. Add ILT from rig-state data if you have it.
  5. Pick the top three causes. Write one action, one owner and one measure for each.
  6. Apply the actions on the next wells. Classify those DDRs the same way every day, not at the end of the well.
  7. After three to five more wells, compare NPT hours per well and per 1,000 ft for the three causes with the baseline. Report what changed and what did not.

A pilot like this needs no new sensors and no system integration. ChatPetroleum can read a set of DDRs and produce the classified time log and the rankings as an Excel workbook, with each row traced to its report.

Where AI NPT analysis goes wrong

  • Classifying without an agreed taxonomy. Then the contractor and operator argue about the labels, not the causes.
  • Trusting accuracy figures from someone else's reports. Test on a sample of your own rows.
  • Ranking only by hours. Frequent short events get missed, and so does ILT.
  • Calling it a root cause. A classified row says what happened. Why it happened still needs an investigation.
  • Measuring once. Without the same classification on the next wells, nobody can show the fix worked.

Our drilling performance solution classifies NPT from your daily drilling reports, ranks repeat causes across wells, adds invisible lost time from rig-state data and tracks the actions well by well. Talk to us about a one-campaign pilot.

Questions people ask

How can AI reduce NPT in drilling?

By reading every daily drilling report, classifying each hour of lost time consistently, and ranking the causes that repeat across wells by hours, count and cost. Engineers then act on the top causes and use the same classification to measure the result. AI provides the evidence; people make the fixes.

What is the difference between NPT and invisible lost time?

NPT is time lost to an event, such as an equipment repair, a wait or a downhole problem, and usually appears in the DDR. Invisible lost time is routine work done slower than the rig has shown it can do, such as slow connections, and is found in rig-state sensor data rather than the report.

How accurate is AI at classifying NPT from drilling reports?

One drilling contractor reported more than 90% accuracy across five classes after manually tagging 40,000 rows. Accuracy on your reports depends on your language, codes and taxonomy, so have an engineer check a sample before the results are used.

How is NPT calculated?

NPT percentage is the NPT hours on a well divided by the total rig hours on that well. To compare wells of different depths, also report NPT hours per 1,000 ft drilled. Cost of NPT is usually NPT hours multiplied by the spread rate.

Do we need real-time data to analyse NPT?

No. NPT classification works on existing daily drilling reports. Real-time rig-state data is needed only to measure invisible lost time and to warn of problems while they build.

Sources

Try Petroleum Chatbot on your own work

Ask a drilling, production or maintenance question now, free. Create an account to keep projects, add your reports and make Excel, Word and PowerPoint files.

Read next